State Senator Mary Lazich (R-New Berlin) represents parts of four counties: Milwaukee, Waukesha, Racine, and Walworth. Her Senate District 28 includes New Berlin, Franklin, Greendale, Hales Corners, Muskego, Waterford, Big Bend, the town of Vernon and parts of Greenfield, East Troy, and Mukwonago. Senator Lazich has been in the Legislature for more than a decade. She considers herself a tireless crusader for lower taxes, reduced spending and smaller government.

I-94 NORTH-SOUTH update: November 9-November 15

News you can use


Here is an update from the Wisconsin Department of Transportation (DOT) for the I-94 NORTH-SOUTH freeway project:

Construction update November 9 –November 15:
I-94 North-South Freeway Project update for Milwaukee, Racine and Kenosha counties

All closures are weather-dependent and subject to change.
New long-term closures are BOLD.

MILWAUKEE COUNTY

  

Monday, NOVEMBER 9

Full Closure of I-94 EAST (SB) exit to Airport Spur 9:30pm – 5:30am

Full Closure of EB Layton entrance ramp to I-94 WEST (NB) 8am- 5pm

Full Closure of I-94 WEST (NB) exit ramp to WB Layton 8am- 5pm on 11/13

Double Lane Closure I-94 WEST (NB) Rawson to Edgerton 9:30pm – 5:30am

Triple Lane Closure I-94 EAST (SB) Rawson to Edgerton 9:30pm – 5:30am

 

Tuesday, NOVEMBER 10

Full Closure of I-94 EAST (SB) exit to Airport Spur 9:30pm – 5:30am

Full Closure of I-94 WEST (NB) exit ramp to WB Layton Until 5pm on 11/13

Double Lane Closure I-94 WEST (NB) Rawson to Edgerton 9:30pm – 5:30am

Triple Lane Closure I-94 EAST (SB) Rawson to Edgerton 9:30pm – 5:30am

Single Lane Closure NB 27th St. and SB 27th St. Layton to Whitaker 6am-4pm

Access closed to/from Bottsford at 27th St.  7am-5pm

 

Wednesday, NOVEMBER 11

Full Closure of I-94 EAST (SB) exit to Airport Spur 9:30pm – 5:30am

Full Closure of Airport Spur WB, entrance ramps from Howell, and ramps to I-94 9:30pm – 5:30am

Full Closure of I-94 WEST (NB) exit ramp to WB Layton Until 5pm on 11/13

Triple Lane Closure I-94 WEST (NB) and I-94 EAST (SB) Rawson to Edgerton 9:30pm – 5:30am

Single Lane Closure NB 27th St. and SB 27th St. Layton to Whitaker 6am-4pm

 

  

Thursday, NOVEMBER 12

Full Closure of I-94 EAST (SB) exit to Airport Spur 9:30pm – 5:30am

Full Closure of Airport Spur WB, entrance ramps from Howell, and ramps to I-94 9:30pm – 5:30am

Full Closure of I-94 WEST (NB) exit ramp to WB Layton Until 5pm on 11/13

Triple Lane Closure I-94 WEST (NB) and I-94 EAST (SB) Rawson to Edgerton 9:30pm – 5:30am

 

Friday, NOVEMBER 13

Full Closure of I-94 EAST (SB) exit to Airport Spur 11pm – 8am

Full Closure of I-94 WEST (NB) exit ramp to WB Layton Opens at 5pm

Double Lane Closure I-94 WEST (NB) Rawson to Edgerton 11pm-8am

Triple Lane Closure I-94 EAST (SB) Rawson to Edgerton 11pm-8am

 

Saturday, NOVEMBER 14
Grange Avenue bridge over I-94 reopen by 5am

 

Sunday, NOVEMBER 15

Only long term closures in effect.

 

LONG TERM CLOSURES IN MILWAUKEE COUNTY
- Single lane closures on NB and SB 27th St between Layton Ave. and Bottsford Ave; both directions of traffic will travel on the new 27th St NB Bridge over I-894/I-43 (two lanes in each direction) until December

- Full Closure of I-894/43 WB entrance ramp from SB 27th St until mid November

- Full Closure of I-894/43 EB entrance ramp from SB 27th St SB until mid December

- Full Closure of I-894/43 EB exit ramp to 27th St until mid December

- Access to 27th St from Bottsford closed. Access from 27th St to Bottsford open for NB right turn only until December

- College Avenue, bridge over I-94, entrance and exit ramps and SW Park and Ride reopen by 5am on November 7

- Grange Ave Bridge over I-94 reopen by 5am on November 14

 

RACINE AND KENOSHA COUNTIES 

 

Monday, NOVEMBER 9

Single Lane Closure I-94 WEST (NB) WI/IL State Line to WIS 50 9:30pm-5:30am

 

Tuesday, NOVEMBER 10

Single Lane Closure I-94 WEST (NB) WI/IL State Line to WIS 50 9:30pm-5:30am

 

Wednesday, NOVEMBER 11

Single Lane Closure I-94 EAST (SB) WI/IL State Line to WIS 50 9:30pm-5:30am

 

LONG TERM CLOSURES IN RACINE AND KENOSHA COUNTIES

- Single lane closure I-94 WEST (NB) Russell Rd to Des Plaines River until December

- Single Lane Closure I-94 EAST (SB) Des Plaines River to Russell Rd (traffic crosses over to NB side of I-94) until December

- Single lane closure of WIS 50 entrance ramp to I-94 EAST (SB) until December

- Full Closure of West Frontage Road between County C and WIS 50 until December

- Single lane closure I-94 WEST (NB) at County G until December

- Single Lane Closure I-94 EAST (SB) at County G (traffic crosses over to NB side of I-94) until December

- Full Closure of I-94 WEST (NB) exit and entrance ramps at County G until August 2010

- Full Closure of I-94 EAST (SB) entrance and exit ramps at County G closed until December

- Full Closure of I-94 EAST (SB) exit ramp at County G Weigh Station until December

- Full Closure of County G bridge over I-94 until December

- Full Closure of I-94 EAST (SB) entrance and exit ramps at County C until December

- Full Closure of County C from 128th St to I-94 until December